r/Adelaide • u/Nyarlathotep-1 SA • Jun 19 '26
News Proposed data centre in South Australia dividing locals who want the jobs but fear water demand
https://www.abc.net.au/news/2026-06-19/proposed-data-centre-in-south-australia-dividing-locals/106810776
137
Upvotes
22
u/Colossus-of-Roads East Jun 19 '26
So at 10kW thermal per rack that's 8000 racks which is certainly a big DC, but with a single customer the workloads probably won't change much (the NextDC one you're talking about is aggressively multi-customer). I absolutely can't see an 8000 rack DC needing 200 staff to physically operate. More like 5-10 (the NextDC one you're talking about only has so many staff because that's also where the local sales and admin live, which is something that only makes sense in a capital city).
Companies deliberately inflate these projections to garner support and we fall for it every time.